WMS App Phases

Implementation phases for the Open Source WMS application.


# Phase Duration
00 Foundation & Citadel IAM 1 day
01 Master Data 2-3 days
02 Inventory & Stock Ledger 2-3 days
03 Supply Chain & Orders 2-3 days
04 Cloud Deployment 1-2 days
05 Frontend (Refine.dev) 3 days
06 Product Onboarding 1.5 days
07 Outlet Lifecycle 1 day
08 Supplier Portal 2 days
09 Price Revision Workflow 1.5 days
10 Data Collection & Import 2 days

WMS uses these composable modules:

wms-app
β”œβ”€β”€ framework-m (core)
β”œβ”€β”€ m-invoice (invoicing)
β”œβ”€β”€ m-india (GST - optional)
└── citadel
β”œβ”€β”€ iam (auth)
└── book-keeper (ledger)

Scope Phases Duration
POC 00-05 ~12 days
Full WMS 00-10 ~19.5 days
+ Modules + m-invoice, m-india ~5 days
Total All ~24.5 days